I lost about a weeks worth of work with the propane tank installation due to bad luck and oversights by the propane dude. It should have taken 4 hours.
This week, I encountered a prep cooler crisis because of lost floor space eaten up by the generator housing. But I overcame the situation with some unique equipment I found that "should" fit perfectly.
I've scheduled a wrap job to cover the entire body of the truck with a giant decal which I will enclose the graphic proofs soon. I chose to wrap the truck instead of painting it because I recently learned that the sign/logo installer needs 2 weeks for the paint to "cure" before applying specific logos.
I realize as I'm writing these posts, how incredibly boring they may be. But hopefully, it will give some insight to the project status.
- Separation wall between kitchen and the cab
- Electrical
- Commercial grade interior panelling
- Gas fitting
- Exterior wrap with logos
Original completion date: July 3rd
Revised completion date: July 15th